Ted Neitzke: The no-disruption statement and the later construction-hour limits
Contradicted by the record
Exact statement
“Since data centers don’t manufacture anything, they don’t add disruptive noise, pollution or traffic.” [1]
Ted Neitzke, Potential For New Development — A Letter From Mayor Neitzke, January 8, 2025
Neitzke made the statement in an official January 8, 2025 letter that said the City had been approached by a developer specializing in identifying and developing data-center sites.[2]
What the record shows
Nearby residents complained about noise and light pollution as well as traffic caused by nonstop, 24-hour weekday construction at the Vantage campus.[3] On March 19, the Plan Commission unanimously amended the plan to limit outdoor construction and deliveries to 6 a.m.–8 p.m. Monday through Saturday, reduce lighting to security levels after 8:30 p.m., and let the amendment take effect April 18.[4][5] Neitzke said the benefits of accelerating construction were not worth the additional inconvenience and that the overnight work was too disruptive and needed to end.[6]
“The overnight work is simply too disruptive and needs to end.” [7]
Port Washington limits construction hours for data center project after complaints, March 19, 2026
Context
Wisconsin Public Radio reported that construction was then allowed 24 hours a day on weekdays and that residents complained about noise, light pollution and traffic from the nonstop work.[3] The amendment permits 24-hour indoor work Monday through Friday, and indoor work until 11:59 p.m. Saturday, only after buildings are fully enclosed and the City Engineer approves the site review.[8] The later record addresses construction impacts at this project rather than the completed facility’s eventual operating impacts.[9][10]
Analysis
The January statement broadly said data centers do not add disruptive noise, pollution or traffic.[10] The later project-specific record documents resident complaints about construction noise and traffic, a unanimous restriction on outdoor construction hours, and Neitzke’s conclusion that the overnight work was too disruptive.[11][12][13] That comparison is limited to documented construction impacts and does not claim that the completed facility will have the same operating effects.[14][10]
Sources
Statement source
Potential For New Development - A Letter From Mayor Neitzke — City of Port Washington, Wisconsin
Pinpoint: Official letter body, paragraph beginning “Since data centers don’t manufacture anything”.
Record source
Port Washington limits construction hours for data center project after complaints — Wisconsin Public Radio
Pinpoint: Paragraphs beginning “Construction on the $15 billion Vantage Data Centers campus…” and “In a statement, Port Washington Mayor Ted Neitzke IV…”.
Every source on this page
Each numbered mark in the text links here. Every excerpt is quoted word for word from the source.
Potential For New Development - A Letter From Mayor Neitzke — City of Port Washington, Wisconsin
Where: Official letter body, paragraph beginning “We have been approached by a developer”
“A data center is a facility that companies like Google, Microsoft and others build to securely house their most powerful computers. Since data centers don’t manufacture anything, they don’t add disruptive noise, pollution or traffic. They do add really good jobs, but on a scale that is easily manageable for a city our size.”
Potential For New Development - A Letter From Mayor Neitzke — City of Port Washington, Wisconsin
Where: Official letter body, paragraph beginning “We have been approached by a developer”
“We have been approached by a developer that specializes in identifying and developing sites for data centers.”
Port Washington limits construction hours for data center project after complaints — Wisconsin Public Radio
Where: Paragraph beginning “Construction on the $15 billion Vantage Data Centers campus”
“Construction on the $15 billion Vantage Data Centers campus is currently allowed to occur for 24 hours a day during weekdays. That has angered some nearby residents, who have complained about noise and light pollution as well as traffic due to the nonstop construction.”
Plan Commission Meeting Minutes – March 19, 2026 — City of Port Washington, Wisconsin
Where: PDF p. 1, item 4, motion amending Condition #8, paragraph 1
“Outdoor construction activities, including exterior construction, earthwork, site preparation, equipment operation (including idling) and site work shall be between the hours of 6:00 a.m. to 8:00 p.m., Monday through Saturday.”
Port Washington to Limit Outdoor Work Hours at Data Center Site — City of Port Washington, Wisconsin
Where: PDF p. 1, first three paragraphs and bullet list
“Mayor Ted Neitzke IV made a motion to amend the previously approved building, site and operations plan for the project, imposing a new limit on outdoor construction activities to between the hours of 6 a.m. and 8 p.m. Monday through Saturday.”
Port Washington to Limit Outdoor Work Hours at Data Center Site — City of Port Washington, Wisconsin
Where: PDF p. 1, paragraph beginning “Allowing 24-hour outdoor construction work”
“But based on what we have heard from nearby residents, the benefits of speeding up the construction timeline are not worth the additional inconvenience. The overnight work is simply too disruptive and needs to end.”
Port Washington to Limit Outdoor Work Hours at Data Center Site — City of Port Washington, Wisconsin
Where: PDF p. 1, paragraph beginning “Allowing 24-hour outdoor construction work”
“But based on what we have heard from nearby residents, the benefits of speeding up the construction timeline are not worth the additional inconvenience. The overnight work is simply too disruptive and needs to end. With tonight’s vote by the Plan Commission, 24-hour work on the site will wind down over the next few weeks.”
Plan Commission Meeting Minutes – March 19, 2026 — City of Port Washington, Wisconsin
Where: PDF p. 1, item 4, motion amending Condition #8, paragraph 2
“Once buildings are fully enclosed and upon site review and approval by the City Engineers, Interior construction activities shall be 24 hours a day, Monday through Friday and until 11:59 p.m. on Saturdays.”
Plan Commission Meeting Minutes – March 19, 2026 — City of Port Washington, Wisconsin
Where: PDF p. 1, item 4 heading and motion amending Condition #8
“AMENDMENT TO BUILDING, SITE AND OPERATIONS PLAN - Consideration and Possible Action to Amend the Hours of Construction for the Vantage Data Center Project”
Potential For New Development - A Letter From Mayor Neitzke — City of Port Washington, Wisconsin
Where: Official letter body, paragraph beginning “We have been approached by a developer”
“Since data centers don’t manufacture anything, they don’t add disruptive noise, pollution or traffic.”
Port Washington limits construction hours for data center project after complaints — Wisconsin Public Radio
Where: Paragraph beginning “Construction on the $15 billion Vantage Data Centers campus”
“That has angered some nearby residents, who have complained about noise and light pollution as well as traffic due to the nonstop construction.”
Plan Commission Meeting Minutes – March 19, 2026 — City of Port Washington, Wisconsin
Where: PDF p. 1, item 4, motion amending Condition #8
“Outdoor construction activities, including exterior construction, earthwork, site preparation, equipment operation (including idling) and site work shall be between the hours of 6:00 a.m. to 8:00 p.m., Monday through Saturday.”
Port Washington to Limit Outdoor Work Hours at Data Center Site — City of Port Washington, Wisconsin
Where: PDF p. 1, paragraph beginning “Allowing 24-hour outdoor construction work”
“The overnight work is simply too disruptive and needs to end.”
Plan Commission Meeting Minutes – March 19, 2026 — City of Port Washington, Wisconsin
Where: PDF p. 1, item 4 heading and paragraphs 1–2
“Consideration and Possible Action to Amend the Hours of Construction for the Vantage Data Center Project”
Correction or added context
See an error or a fuller primary source? Both options below open a pre-addressed draft identifying this entry; this site does not collect or send form data.